Needs Engineering2
PSO-4501UNASSIGNED
Crestview Steel
Baghouse fan replacement โ€” 200HP ID fan
Waiting: 62 days
ARM: Adam Harris
Priority: HIGH
PSO-4530UNASSIGNED
Alcoa
Potline ventilation fan โ€” field service inspection
Waiting: 39 days
ARM: Adam Harris
In Progress5
PSO-4488IN PROGRESS
Summit Steel Works
Precipitator fan rebuild โ€” dual 350HP units
Engineer: Marcus Webb
Started: Oct 20 โ€” Day 166
Due: Feb 20
PSO-4520IN PROGRESS
CMC Steel
EAF canopy hood fan upgrade โ€” 150HP
Engineer: Marcus Webb
Started: Jan 25 โ€” Day 69
Due: Mar 20
PSO-4522IN PROGRESS
Novelis
Rolling mill exhaust fan refurbishment
Engineer: Raj Patel
Started: Feb 1 โ€” Day 62
CUSTOMER APPROVAL โš 
Due: Apr 5
PSO-4538IN PROGRESS
SSAB
Reheat furnace combustion air fan
Engineer: Raj Patel
Started: Jan 25 โ€” Day 69
Due: Apr 20
PSO-4542IN PROGRESS
Cleveland-Cliffs
BOF primary gas cleaning fan โ€” field service
Engineer: Dan Kowalski
Started: N/A โ€” Day 0
Due: Apr 25
Buddy Checks Needed2
PSO-4510IN REVIEW
Redstone Steel
Lead: Dan Kowalski
Reviewer: Raj Patel
Drawings ready: Feb 20
WAITING 43 DAYS โš 
PSO-4515BUDDY CHECK
Steel Dynamics
Lead: Dan Kowalski
Reviewer needed
Drawings ready: Feb 24
WAITING 39 DAYS โš 
I&A ENGINEERING REQUESTSIA-2026-0005ยทSummit Steel WorksยทGearboxยทJeff Dawson